PNEG-1820CE Compliant Top Dry Series 2000 AutoflowOperators ManualPNEG-1820Date: 04-10-12
2. Decals10 PNEG-1820 CE Compliant Top Dry Series 2000 AutoflowDC-2166Ear protection must be worn in this areaDC-2166Background: WhiteColors: Black an
PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 113. Fuel and Electrical SpecificationsTop Dry CE Heater SpecificationsFuel SpecificationsElectric
12 PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow4. Electrical InstallationThe electrical supply must be capable of the full demand from the drye
PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 135. Fuel InstallationFuel SupplyThe dryer requires a suitable fuel supply. Refer to fuel specific
14 PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow6. Control PanelDryer Control PanelFigure 6A Moisture Control SwitchDetermines if the grain temp
6. Control PanelPNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 15Load Auger SwitchControls the operation of the drying chamber fill system(s).Swi
16 PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow7. Control SystemElectronic Monitoring Control SystemFigure 7A Electronic Monitoring Control Sys
7. Control SystemPNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 17Setting the DelaysThe following timers are set using the same procedure, but th
7. Control System18 PNEG-1820 CE Compliant Top Dry Series 2000 AutoflowUse the Increase and Decrease buttons to select the correct time or date. Press
PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 198. Fill System Control BoxFigure 8A The fill system control box houses the motor starters for fi
2 PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow
8. Fill System Control Box20 PNEG-1820 CE Compliant Top Dry Series 2000 AutoflowFigure 8B Ignitor and Flame Probe AssembliesFlame probeIgnitor91031246
8. Fill System Control BoxPNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 21Flame Probe, Ignitor and Burner Assemblies Parts ListFigure 8C LP Vapo
22 PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow9. Error Messages and Valve Proving SystemError MessagesBurner * Loss FlameThe flame sensor in b
9. Error Messages and Valve Proving SystemPNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 23Drying Chamber OverflowThe grain level in the drying c
9. Error Messages and Valve Proving System24 PNEG-1820 CE Compliant Top Dry Series 2000 AutoflowGrain High-LimitThe grain temperature in the drying ch
PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 2510. Initial Start-UpDryer CommissioningElectrical1. Carry out earth bonding test per EN60204 and
10. Initial Start-Up26 PNEG-1820 CE Compliant Top Dry Series 2000 AutoflowGas Train (Continued)6. Set burner low-fire pressure.• Set plenum temperatur
PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 2711. Pre-Season ChecksBefore the dryer is filled, inspect the unit and check the operation of the
11. Pre-Season Checks28 PNEG-1820 CE Compliant Top Dry Series 2000 AutoflowDrying ChamberInspect each dump hopper for obstructions.Make sure that the
11. Pre-Season ChecksPNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 29Fill SystemPrepare the wet storage tank to deliver grain to the dryer.Make
Table of ContentsPNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 3ContentsChapter 1 Safety ...
30 PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow12. Autoflow TheoryTop Dry Autoflow Theory of OperationControl Panel Switch Status• Control powe
12. Autoflow TheoryPNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 31During the dump cycle 1/3 of the grain is dumped into the storage chamber.Aft
32 PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow13. Start-Up ProcedureInitial Dryer Start-Up1. With Control Power switch OFF, turn ON the main p
13. Start-Up ProcedurePNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 3312. Set the grain temperature set point as follows:• 82°C Drying temperatu
13. Start-Up Procedure34 PNEG-1820 CE Compliant Top Dry Series 2000 AutoflowNormal Start-UpWhen the dryer is started with grain in the drying chamber
PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 3514. WarrantyGSI Group, LLC Limited WarrantyThe GSI Group, LLC (“GSI”) warrants products which it
This equipment shall be installed in accordance with the current installation codes and applicable regulations, which should be carefully followed in
4 PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow1. SafetySafety GuidelinesThis manual contains information that is important for you, the owner/o
1. SafetyPNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 5Fan/Heater Installation and Operating InstructionsThank you for choosing a Top Dry Serie
1. Safety6 PNEG-1820 CE Compliant Top Dry Series 2000 AutoflowSafety in MaintenanceShut off and lock power and fuel supply to the dryer before enterin
1. SafetyPNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 7Safety Sign-Off SheetAs a requirement of O.S.H.A., it is necessary for the employer to t
8 PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow2. DecalsSafety decals must be read and understood by all people in and around the top dry area.
2. DecalsPNEG-1820 CE Compliant Top Dry Series 2000 Autoflow 9 Isolate and lock from power before removing guards or opening enclosure R